1-800-343-9355

Case Studies

Sulfuric Acid Sewer System

Industry Served : Chemical Processing
» Engineering, Manufacturing, Installation Package
» Partial Underground Installation
» 2500 of 16″ and 8″ Piping Installed Including 4 Teflon Lined MW
» Zero Lost Work Time
» Minimally Flanged Design

PartialUnderground

Installation of FRP Crossover

Industry Served: Pulp and Paper
» Manufacturing and Full Mechanical Install of 2(ea) 6 FRP Crossover Elbows
» Updated FRP Corporate Composite Specifications
» Manufacturing Time: 6 weeks
» Installation Time: 4 days

rsp-case-study-pic-2

rsp-case-study-pic-1

Cooling Water Pipe

Industry Served : Power
» FRP pipe and fittings, onsite technical assistance and training in FRP joining methods
» Large Diameter Pipe P-Series

In 2012, a large independent energy producer contracted RPS to supply approximately 3,000 feet of large diameter FRP cooling water pipe and associated fittings for a project in one of the Caribbean Islands. Besides our competitive offerings, RPS Canada was selected as the supplier of choice due to our proximity to the deep water port of Halifax. Halifax was the main staging location for all equipment leaving Canada for the Caribbean.

rps-case-study-pic 5